WASHINGTON — The Army has acknowledged an MV-75 delivery delay for testing, saying it will not receive the first tiltrotor long-range assault aircraft by its original end-of-year target, according to the service’s acquisition office.
“Delivery of the MV-75 for testing will not occur by the end of 2026. The program made deliberate efforts toward this goal while making measurable program progress,” a spokesperson for the Office of the Assistant Secretary of the Army for Acquisition, Logistics and Technology said on Nov. 20. The spokesperson also said the Army still expects to complete development and testing in about half the time of comparable historical programs.
In January, then-Army Chief Gen. Randy George said the service planned to accept an aircraft for testing by the end of 2026. A subsequent funding shortfall disrupted communications between the Army and Bell, the program’s prime contractor, contributing to the missed delivery objective.
The Army has not set a revised date to receive the first test aircraft, the acquisition office said. The service and Bell, a Textron subsidiary, are working on an updated, resource-loaded integrated schedule and a schedule risk analysis to establish achievable milestones at an affordable cost.
MV-75 delivery delay tied to funding gap
Bell was selected in late 2022 to build the MV-75 Cheyenne II under the Future Long Range Assault Aircraft program. The Army has said the aircraft is designed to fly twice as fast and twice as far as current assault helicopters and is expected to begin replacing portions of the UH-60 Black Hawk fleet once fielded.
The MV-75 delivery delay follows a funding shortfall that surfaced after the Army had spent nearly all available fiscal 2026 funds for the program by July, according to Textron’s latest quarterly filing. The company said it continued work while reducing spending to manage the gap.
In July, the Army sought to reprogram $350 million to support the build and test of eight prototype tiltrotors. Lawmakers approved the request in the third quarter. About $300 million was subsequently obligated through contract changes to cover costs already incurred by the company and suppliers, Textron CEO Lisa Atherton said in October on an earnings call.
According to the Army acquisition office, Bell chose to continue some activities at its own risk without additional funding. Both the company and the service said communications halted during the funding lapse and resumed on Sept. 28 when the reprogrammed funds arrived.
“Once funding was received, normal contract execution and communications resumed. The funding gap affected the planned schedule. The Army and Bell are now assessing those effects and updating the program schedule and risk analysis to establish realistic, affordable milestones and delivery dates,” the spokesperson said, adding that the restart emphasizes disciplined execution within available budgets.
Budget outlook could affect production timing for MV-75
Uncertainty around the fiscal 2027 budget could compound schedule risk. The Army has requested more than $2 billion for the MV-75 in FY27, all under discretionary spending. Delays in approving those funds could push back the first low-rate initial production contract.
“With the start of the fiscal year in a continuing resolution, we’d expect a possible push in the timing of the LRIP award. Previously, we were thinking Q4 into Q1 of next year,” Chief Financial Officer David Rosenberg said in October.
Despite schedule pressure, Army Undersecretary Michael Obadal said the aircraft remains a priority and that the service is committed to fielding it as soon as possible. “Getting the MV-75 into hands of Army aviators will be the culmination of one of the biggest Army acquisitions. The Cheyenne meets the endurance and close combat demands of large-scale combat operations,” he said, adding that it extends the range for delivering and repositioning assault forces and is a joint force priority.
Program timelines have been in flux for months. In April, Maj. Gen. Clair Gill, then serving as the Program Executive Officer for aviation, declined to set dates for first flight or production start, saying, “It’s going to happen when it’s going to happen. So we are moving as fast as we can.”